Project Controls:
LEVEL 3 PROJECT SCHEDULE

Execute the Work

For the purpose of WorkFace Planning: the ideal level 3 schedule is made up of Construction Work Packages (CWPs) that each represent a single discipline and less than 40,000 work-hours. The schedule should also be based on the Path of Construction. The Engineering portion of the schedule should show completion dates for Engineering Work Packages (EWPs) and 1 EWP must equal 1 CWP. The level 3 Project Schedule is a deliverable from the Project Management’s Project Controls Team to the Constructor and the 3D Model Administrator prior to the start of construction.