Project Controls:
RULES OF PROGRESS

Execute the Work

This standard establishes the rate at which the construction team will earn value (EV) from the Installation rates. The construction team may earn 10% of the total Planned Value (PV) for a spool of pipe when it is received on site and then another 30% when it is rigged into place etc. This table is a deliverable from the Project Management’s Project Controls Team to the 3D Model Administrator , prior to the start of construction.